No | Kode Rincian | Uraian | Nilai | Sumber Dana |
---|---|---|---|---|
1 | 5.3.4.03. | Membayar 1 unit Panggung Portable 6 x 8 meter dan 1 Paket Pohon Tanam tgl 25 Apr 25 | 41.800.000 | PBP |
2 | 5.3.4.03. | Membayar 1.500 m2 Paving tgl 5 Mei 2025 | 199.228.500 | PBP |
3 | 5.3.4.03. | Membayar 110,40 m3 Pasir Pasang Paving, 164,40 m3 LPA, 18,40 Sirtu dll tgl 3 Jun 25 | 90.123.840 | PBP |
5.3.4.03. Belanja Modal Gedung, Bangunan, Taman - Bahan Baku/Material (Sub Jumlah) : | 331.152.340 | |||
Total Keseluruhan: | 331.152.340 |